Maintenance of Time- and BOM-dependent Routing Parameters

Description

With Release 4.0A, time-dependent maintenance of the scrap factor, cycle time, and load factor is possible through a predefined period split either in the material master or the routing.

Data is saved in the PLPLAN_PARAM table. You can save the parameters either to a standard routing, or to a standard routing connected to a BOM. When the plan is disaggregated, the scrap factors that were originally maintained in the plan, as well as standard values 1 and 2, will be temporarily overwritten.

You can carry out this transaction in the process overview of the routing or through material planning 2 in the material master.

It is only possible to maintain data for standard routings. Referenced routings with referenced operations, for example, cannot yet be maintained.

Change system parameters in customizing

No changes in Customizing are required.