Transfer of Logistics Confirmations to Incentive Wages

Description

The connection from Logistics to Incentive Wages has been changed for Release 4.0A. Tables and reports used previously have been replaced.

If you used to retrieve confirmations using the RPWI1000 report, you can start this report one more time to retrieve all of the confirmations remaining in the AFRUHR interface table.

Then, schedule the RPWI1000 report (instead of the old RPWI1000 report) to read the new LSHR interface table.

If you want to use this functionality for distributed systems in the future, start the old RPWI1000 report after the release update but before distributing the systems. The AFRUHR table is no longer required in the HR system.

Change system parameters in customizing

Schedule the Integration with Logistics: Read interface file and create session report (RPWI1100) in the Work Time Durations from Logistics section of the Implementation Guide (IMG).

Dependent functions

To reorganize the AFRUHR interface table, use the RPWI4000 report. Execute this report after you retrieve the last confirmation using the old RPWI1000 report.

Then, instead of using the RPWI1000 report, use the new RPWI4100 report to reorganize the LSHR interface table.

If you want to use this functionality for distributed systems in the future, start the old RPWI4000 report after the release update, but before distributing the systems.