New functions in order confirmation

Description

For 4.0A there are the following new confirmation functions:

Progress confirmation is a special type of confirmation: When an operation is confirmed preceding operations and sub-operations are automatically confirmed.
In contrast to milestone confirmation, with progress confirmation you do not need to plan in advance the operation you want to confirm. You can select every operation that can be confirmed.
You create a progress confirmation in the production control menu. There you choose Confirmation -> Create -> For operation -> Progress confirmation
There is a new function you can use to start an actual costs calculation again after an error has arisen in a previous calculation within confirmations.
The function offers the following options:
You reach this function in the production control menu in Confirmation -> Recalculate actual costs .