From Release 4.0, you can copy planned costs from networks and
orders for projects into a plan version. This is a separate process
from copying the manual plan values from the WBS element. Go to the
Planning menu and choose Costs/Revenues -> Copy
planning -> Orders/networks.
The following functions are available:
Selection of the objects affect using the logical database
Inclusion of the costs for all selected orders and networks in
the copy
The following are not copied:
Manuall plan values in the WBS elements
Sales orders
CO internal orders
Evaluation of plan versions in the information system
You cannot edit the version.
Deletion of planned values from plan versions
You cannot delete values from plan
version 000
Overwriting existing plan versions
You cannot overwrite plan version
000.
Changes to the interface
In the Project Planning menu, choose Costs/reveues
-> Copy planning, then
Orders/networks.