rough-cut planning profile

Production Planning and Control (PP)

Tool with which resource leveling can be carried out from a long- or medium-range viewpoint.

It records future requirements of one or more of the following resources:

These resources can be tied to any key figure (e.g. production) for any material, product group, or characteristic values combination.

Rough-cut planning profiles are time-phased, but the precise scheduling of resource requirements depends on how the scheduling levels are configured in Customizing.

The resource load for work center capacities can be displayed in the SOP planning table at runtime. The resource load for the other resources are shown in standard analyses.

BOM explosion does not take place in rough-cut planning profiles.