Copying a Responsibility

Prerequisites

You first create an activity group by selecting reports, transactions, and tasks from the Menu and Task screens. Then create one or more responsibilities on that activity group.

Procedure

  1. On the Activity Group Basic Data: Change screen, select the responsibility you want to copy.
  2. Choose Responsibility ® Copy.
  3. The Responsibility Copy dialog box appears.

  4. You can change the object abbreviation, and the object name.
  5. Choose Continue.

Result

The copied responsibility is displayed in the tree structure in the Activity Group Basic Data: Change screen. You must now regenerate the authority profile for the new responsibility. If an authority profile has been generated for the original responsibility, the authorization values are copied (including the organizational levels).