Assign actual values

In this step, you make specifications on the use of the budget category. You specify whether it is a budget category

In this way, the system can assign the actual values of the investment measure in reporting to the individual budget categories:

Requirements

You must have carried out the step

Define budget categories.

Standard settings

SAP provides the budget categories "capital" and "expense".

Activities

Assign an appropriate settlement indicator to your budget categories. When you make an entry in the table, therefore, make sure that the program type and budget category are consistent.

Note

You can make additional assignments using an enhancement project.