Define Planning Profiles for CO Production Orders

To plan values on orders, you must create your own planning profile or use an existing one.

In this step you create new profiles or change existing ones.

The following parameters are relevant when planning overall values on internal orders:

Here, you set the following:
Here you can store default values for the cost element and cost center groups, as well as for the planning parameters to be set when you access the planning function. These values can be overwritten in the application.

Requirements

You have completed the following steps and maintained parameters so that they are available as default values:

Define costing variant

Activities

1. Choose "Details" to check the planning profiles contained in the standard SAP System.
2. If necessary, alter the existing planning profiles to suit your requirements or create new planning profiles with "New entries".
3. Enter the plan profile in the order type.