Define Date Control

In cost estimates without quantity structure, the date control ID determines the dates on which the items are valuated. These dates determine the following:

Date control determines which dates are proposed as a default or displayed when costing, and whether these dates can be changed.

If you intend to calculate variances with reference to the cost estimate, you should make sure that the cost estimate is valid in the periods in which you will calculate variances.

Standard Settings

The standard system contains predefined date control IDs. You can use these without further changes.

Actions

Check whether the existing date control IDs meet your requirements.

1. Choose New entries.
2. Enter an alphanumeric key and a text for the date control ID.
3. Specify which dates can be proposed by the system and whether the user can change the dates during costing.
4. Save your entries.